The county review committee approved site plan file WO-0130Sp at 243,360 square feet of industrial space, and a lot line adjustment (WO-0322) for the same applicants.
The exact site has not been made public, so it is shown at the middle of Woolwich Township.
Project phase
- Application filed
- Hearing held
- Approved
- State permits pending
- Under construction
- Fully built
- Town
- Woolwich Township
- County
- Gloucester County
- Type
- Commercial
- Latest step
- Jul 28, 2026
The project
A warehouse and distribution facility at 242 Oak Grove Road in the Regional Center West Redevelopment Area, listed by the county at 243,360 square feet.
What usually comes next
Projects like this often need county or state permits before any work starts on the land. Some skip that step and start building.
The Township Committee agenda listed R-2026-288 and R-2026-289, consenting to the assignment of the redevelopment agreement and the financial agreement from 2024 Oak Grove Road Woolwich, LLC to USICVII 242 Oak Grove Urban Renewal, LLC for a warehouse and distribution facility.
Hillwood Development and Ferber asked the Township Committee to transfer the redevelopment and financial agreements for 242 Oak Grove Road to a joint venture, aiming to close on the site in July 2026 and start building in early to mid 2027. The committee asked for a resolution adding Hillwood as co-redeveloper at its June 1 meeting.
The Township Committee agenda listed a presentation by Hillwood on the reassignment of the Ferber warehouse project.
The Joint Land Use Board adopted Resolution 2026-18, granting an extension of final major site plan approval to Oak Grove Road Woolwich, LLC for 242 Oak Grove Road.
Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.