Cumberland CountyCommercial

Project phase

  1. Application filed
  2. Hearing held
  3. Approved
  4. State permits pending
  5. Under construction
  6. Fully built

No new board documents in about 90 days. The stage shown is the last step it reached.

Town
Upper Deerfield Township
County
Cumberland County
Type
Commercial
Latest step
Jun 24, 2026

The project

A 94,739 sq ft warehouse addition (Phase I) and a 201,603 sq ft production facility (Phase II) joined to the existing 86,350 sq ft warehouse on Parsonage Road.

What usually comes next

Homes usually go on sale, or buyers start closing, as parts of the project are finished.

Steps so far

  1. The Cumberland County Improvement Authority reported a construction milestone event at Lassonde, with the expansion expected to be completed in the coming months.

    Under constructionSource: Cumberland County Improvement Authority · Read the document
  2. The board granted preliminary and final major site plan approval for the Phase II production facility and memorialized the Phase I approval as Resolution 2-2025.

  3. The board granted preliminary and final major site plan approval for the Phase I warehouse addition.

  4. The board deemed the Phase II production facility application conditionally complete, with a waiver of the full environmental report.

  5. The Upper Deerfield Township Planning Board deemed the Phase I warehouse addition application conditionally complete.

Back to the development map

Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.