Burlington CountyCommercial

The whole town is outlined because this applies across Pemberton Township, not to one site.

Project phase

  1. Application filed
  2. Hearing held
  3. Approved
  4. State permits pending
  5. Under construction
  6. Fully built

No new board documents in about 90 days. The stage shown is the last step it reached.

Town
Pemberton Township
County
Burlington County
Type
Commercial
Latest step
May 8, 2026

The project

Ordinance No. 10-2026 amending Chapter 190, Zoning, to prohibit building and operating data centres anywhere in the township.

What usually comes next

Projects like this often need county or state permits before any work starts on the land. Some skip that step and start building.

Steps so far

  1. Pinelands Commission minutes report that staff found ordinances from Monroe, Pemberton and Waterford prohibiting data centres raise no substantial issue with the Pinelands plan.

  2. Pemberton Township Planning Board reviewed Ordinance No. 10-2026, found it not inconsistent with the master plan, and directed a letter of findings and recommendations to council.

Back to the development map

Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.