The board adopted Resolution 2021-16, an administrative approval for Knight Owl Holdings V, LLC, by unanimous roll call.
The exact site has not been made public, so it is shown at the middle of East Greenwich Township.
Project phase
- Application filed
- Hearing held
- Approved
- State permits pending
- Under construction
- Fully built
No new board documents in about 90 days. The stage shown is the last step it reached.
- Town
- East Greenwich Township
- County
- Gloucester County
- Type
- Commercial
- Size
- 700,000 sq ft
- Latest step
- Dec 9, 2021
The project
A 700,000 square foot warehouse distribution centre on the north-east side of Democrat Road, about 1,650 feet south of Swedesboro Avenue: 679,000 square feet of warehouse and 21,000 square feet of office, with 146 truck parking spaces and 400 passenger vehicle spaces. The board granted preliminary and final major site plan approval together with bulk and parking variances.
What usually comes next
Projects like this often need county or state permits before any work starts on the land. Some skip that step and start building.
The Combined Planning/Zoning Board deemed application 2020-10 complete, took no public comment, and granted preliminary and final major site plan approval together with bulk and parking variance approval, 9-0.
Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.